By Stephen Simon
The Federal Government has suspended the construction of a pedestrian bridge at the Aseese section of the Lagos-Ibadan Expressway following a massive traffic gridlock that left motorists stranded for more than 20 hours.
The suspension came after the traffic diversion introduced to facilitate installation of the bridge triggered severe congestion along the busy highway.
The construction, being handled by the Federal Ministry of Works in collaboration with CBC Construction Company, was initially scheduled to run from November 18 to November 22.
Under the traffic management arrangement, inbound Lagos-bound motorists were diverted towards the Lagos carriageway before rejoining their normal route at a designated point opposite Christ Embassy.
However, the diversion reportedly caused traffic congestion from about 2pm on Wednesday, with movement remaining severely disrupted until Thursday afternoon.

Some commuters reportedly abandoned their journeys, while commercial drivers and motorcyclists increased fares significantly.
The Ogun State Traffic Compliance and Enforcement Agency subsequently announced the indefinite suspension of the diversion pending further directives.
The acting Controller of the Federal Ministry of Works in Ogun State, Richard Adeleye, confirmed that the construction was suspended because of the traffic situation.
The development has renewed concerns about traffic management and the need for adequate alternative routes whenever major infrastructure projects are undertaken along heavily travelled highways.